Cabling Business Magazine
May 2003 issue
ICON: Seize the Opportunity
Using Computer Software to Bid a Cabling
Project
By Peter J. Buitenhek
"You
ask me if I keep a notebook to record my great ideas.
I've only ever had one." |
|
|
-Albert Einstein, theoretical physicist (1879-1955) |
"Everything should
be made as simple as possible, but not simpler." |
|
My involvement
with cabling started in 1979. Back
then, communications cabling was simple, each manufacturer had a
proprietary scheme. Analogous to driving your car from San Diego to
Los Angeles, you would use the IBM Highway if you owned IBM computers
- the DEC Highway for DEC computers and so on. Today, for computer
communications we are using one structured highway and letting
standard interfaces do the busy work. These "communication standards"
are a credit to IEEE, NEC, EIA/TIA and BICSI. A simple RJ-45 jack and
cable allow near-virtual communication connection to hubs, routers,
NIC's and computers. Constantly evolving funneled standards and
innovative manufacturing processes have yielded cabling products that
are all their marketing people claim them to be. Many contractors
bidding communications cabling projects still use "seat-of-their
pants" practices. Variances in technician/estimator ability and
training nearly out-weigh the technical advances of communications
cabling and hardware. Larger organizations utilized formalized
training programs and cumbersome prepackaged estimator/design
software. Conversely, smaller cabling companies only have homegrown
software or best-guess practices to bid sophisticated projects. On
a
recent cabling installation project for a convention center, the
owner received seven bids from cabling contractors that ranged from
$91,000 to $235,000. Prior to this bid, the owner did the homework
with the top supplier/top material vendor (Graybar and Belden) to determine
baseline material costs: $89,000.
Obviously, major items like tax; labor and profit dollars were over-looked by some contractors and over-extended by others.
Where to Start?
The first question that always pops up is, "Are computer software
programs reliable enough to give me consistent winning bids?"
No. The results are only as good as the person entering the data for
analysis. If your design includes all possible components and
associated tasks you will, most likely, not be the lowest bidder.
However, if you include all possible components and tasks but bid the
project at a lower gross profit margin, knowing you may not need
every item, you will find that lower GPM will rise with every task
completed under budget. So challenge the project managers and
technicians to excel at their task and include a bonus in your plan
if they meet the challenge.
BidPro Sheet Breakdown and Descriptions
1
|
The Parameter Sheet feeds all other sheets in
the workbook. Begin by setting all regular parameters here and
save this copy as your company's baseline. This way when you
call up BidPro, all company parameters are already set; all you
need to do is add labor hours and material costs to start the
BidPro calculations.
|
|
a
|
Did a
site survey take place? "No" may indicate
many material and labor items are estimated. |
|
b
|
List Labor and Material (if applicable) sales tax
rate |
|
c
|
Are subcontractors involved? Labor and Material
costs apply along with markup |
|
d
|
Miscellaneous Material cost and possible freight
charges |
|
e
|
Add charges:
-permits and license costs
-parking per day
-driving mileage per day beyond company standard
-Per Diem
-Prevailing Wage
-Premium or weekend rates |
|
f
|
Burdened labor rate markup |
|
g
|
Labor Markup Percentage |
|
h
|
Material Markup Percentage |
|
i
|
Any other direct job overhead costs |
|
j
|
Labor Force breakdown by name, area and Raw Pay
Rates |
2
|
The Labor Sheet allows up to 500 task entries. Each task is
associated with a specific classification of worker WBS (Work
Breakdown Structure) that is set to your baseline parameters.
Labor hours for all tasks can be described in total hours or
by quantity-per minute (i.e., 300 jack terminations at 3.5
minutes each equals 17.5 labor hours). In addition, all
worker classifications are summarized at the bottom of the
sheets to provide a quick overview of personnel allocation.
|
3
|
The Material Sheet can take up to 500 material entries (each
with Description, Part #, Vendor #, Color/Other, Unit Cost,
Markup and Extended Price). All material quantities and
overall pricing are summarized at the page bottom for review.
|
4
|
The Summary Sheet is comprehensive, depicting all entry
calculations and is used to fine-tune all calculations. Raw
labor cost, non-productive time, prevailing wage, direct
overhead charge, burden and sell pricing are depicted. The
material section of this sheet allows more fine-tuning
(example: add material items at no mark-up charge). The
workday length and desired workweek are preset to eight hours
per day five days per week, this can be user modified (i.e.,
10 hour day, four days per week). The project duration is
calculated using the total Labor Line Items, total hours and
the work-day-work-week scenario into Days/Weeks/Months.
|
5
|
The Margins Sheet is broken down into another six sections to
better determine your specific company needs. Section 1 uses
your entire Parameter/Labor/Material and Summary Sheet inputs
and calculates a project sell price and GPM. Section 2 allows
the user to adjust individual GPM per item (i.e., Material,
Labor, Mileage, Per Diem, etc.). Section 3 allows the user to
set the desired GPM and BidPro calculates sell prices using
your labor/material/other costs. Section 4 allows the user to
set the desired sell price and BidPro calculates the GPM.
Section 5 uses your Parameter Sheet GPM company project
baseline. Finally, BidPro will calculate the user chosen
project cost and convert the final costs into Time and
Material rates.
|
6
|
The
Cost Chart is a Microsoft® Excel-based graphic
depicting four cones (and portions of cones) as category
costs (i.e., Labor, Material, Subcontractor and Other). The
largest cost item will be shown as a complete cone. The
remaining three will be portions of cones to ascertain costs
relationships.
|
7
|
The
Margins Chart is a Microsoft® Excel-based graphic
depicting the six profit based options that make project
bidding easy within BidPro.
|
Summarization
The Parameter Sheet sets the company specific information. Project
tasks are defined on the Labor Sheet and assigned technicians are
applied to these tasks. The Material Sheet list all expected material
items needed for task completion. The Summary Sheet is used to
fine-tune all Parameter, Labor and Material Sheets supplied costs.
The Margins Sheets allows up to six sell options based on desired
company profit. The inputs will yield the desired profit options
within minutes.
Start to Standardize
Material and labor costs are a good starting point for bid
standardizing. By utilizing expected costs for the project, we can
structure the bid sell price based on profit margin. If any of these
expected costs do not materialize, we can use these monies to
purchase test equipment, pay for overruns or keep as profit.
Labor Force: consulting services, drafting, site survey, as-built
drawings, installation, project manager and administrative services
all require specific skills. List their associated raw pay rates
(employee pay prior to company costs for 401K, healthcare,
disability, et al). List these services by category, name or
assignment.
WBS
|
Employee Classification
|
Standard $
Range
|
This Bid Raw $
|
01
|
Albert-Project Manager
|
$20.25 - $25.00
|
$16.00
|
02
|
Bryan-Lead
|
$15.00 - $22.50
|
$12.00
|
03
|
Charlie-Mid
|
$12.00 - $19.00
|
$7.00
|
04
|
David-Tech
|
$14.00 - $16.00
|
$15.00
|
05
|
Average A/B/C/D
|
$11.00 - $13.00
|
$12.50
|
06
|
Apprentice(0-2 years)
|
$8.25 - $10.00
|
$10.00
|
07
|
Supervisor
|
$28.00 - 32.62
|
$30.00
|
08
|
Technician III
|
$11.65 - $33.36
|
$25.00
|
09
|
Technician II
|
$25.00
|
$20.00
|
10
|
Technician I
|
$18.53 -$28.51
|
$15.00
|
11
|
Warehouse
|
$10.00 - $12.36
|
$12.00
|
12
|
Network Programmer Sr.
|
$55.00 - $75.00
|
$65.00
|
13
|
Network Programmer
|
$35.00 - $65.00
|
$45.00
|
14
|
Sales Lead
|
$35.00 -$45.51
|
$35.00
|
15
|
Sales
|
$30.00 - $37.36
|
$30.00
|
16
|
Marketing
|
$40.00
|
$25.00
|
|
|
The 16 WBS or work-breakdown-structure numbers will
later be used to assign specific employees or groups to tasks. Your
Standard $ Range versus This Bid Raw $ could be helpful in
determining the competitiveness of the final bid. Higher priced
people will usually increase the labor pool cost. Conversely, the
higher paid people should lower the total task labor hours since
experienced people will take less time to accomplish tasks. As
depicted in Figure 1 Labor Raw Cost, Employee Classification can be
specific named people, groups of people or areas of expertise.
Project Manager pay-rates may vary within your organization so set
the range and actual pay rates to determine exact labor costs.
Figure 2 Burden Rate Percent
Since raw labor costs do not reflect the company's
actual cost only the employee pay, the burdened labor rate will be
required. Health benefits, 401K and disability/unemployment insurance
are some areas that cost your company money in addition to the actual
raw pay. Usually a 30 percent burden rate will cover most employee
expenses. Therefore, if one hour of the project manager (we'll use
Albert as an example) were to be used; the burdened labor rate would
be the raw labor cost times one plus the burden rate (1+0.3=1.3)
Figure 3 Burden Labor Cost
Employee
|
Labor Hours
|
Raw Cost
|
Burdened Cost
|
Albert - PM
|
1
|
$16.00
|
$20.80
|
Thus Albert would cost the company $20.80 (16 x 1.3).
This value will then be used to calculate the sell price of Albert to
the customer.
Figure 4 Labor Markup Percent
The sell price per hour of Albert would incorporate
the burden and labor rates to give Albert a sell value of $33.28 per
hour (20.80 x 1.6).
Figure 5 Margin Calculation
Labor Markup %:
|
Cost
|
Sell Price
|
Calculated Gross Profit
|
60%
|
$20.80
|
$33.28
|
37.5%
|
Notice the calculated gross profit margin of 37.5%.
This value depicts net sales minus cost of sales or basically how
efficiently a company markets their service. As an example, if the
labor cost was $30.00 and the sell price $33.28, the corresponding
profit of $3.28 would provide a gross profit margin (GPM) of 9.9%.
Thus, a higher GPM will reflect higher profit dollars.
Formula for Gross Profit Margin
Gross Profit Margin (GPM) x 100% = (Sell Price minus Cost) divided
by Sell Price. Additionally, some companies have indirect costs
(additional employee benefits or executive travel benefits) that
affect the company bottom-line costs but do not show up in labor cost
figures. Therefore, the Direct Job Overhead (DJO) markup can be used
in addition to burden margin for this project.
Figure 6 DJO
* Direct Job Overhead %
|
15.0%
|
This markup will add overhead charges to the raw labor
cost only; but will not markup that cost with the 60% Labor Markup.
The sell price is equal to the cost and thus the profit margin will
reflect 0.0% GPM. The net effect of DJO is to add cost to the
equation without the associated sell markup, which will reflect a
less efficient operating company. The * signifies this quantity does
not have a sales markup figure.
Figure 7 Margin Calculations with DJO
Category listed on Parameter Sheet
|
Parameter set on Parameter Sheet
|
Cost
|
Sell Price
|
Calculated
Gross Profit %
|
Labor Markup %:
|
60%
|
$20.80
|
$33.28
|
37.5%
|
* Direct Job Overhead %:
|
15.0%
|
$2.40
|
$2.40
|
0.0%
|
Another area
of additional labor cost could be "Non-productive" time. Non-Productive
time is available to
incorporate the time a technician is on-site waiting for other
trades, comebacks, meetings etc. The Non-Productive time is the total
number of hours per day counted on to complete the task but is really
not available. To account for this lost time, we can incorporate an
add-on charge per hour to that technician base rate. Since most teams
break at the same time and the same duration, this information is
converted to an average cost/hour for each technician and added to
all technician hourly rates. A 15-minute break every two hours
equates to one hour of non-productive time per eight-hour day.
Figure 8 NPT
* Non-Productive Time (hours/day):
|
1.00
|
For Albert the PM, the 1.00 per hour of NPT would
result in an additional labor cost of $2.00 per hour ($16.00 per hour
divided by eight hours per day). The equivalent raw labor rate for
Albert would be $16.00 base plus $2.00 NPT plus $2.40 DJO = $20.40.
Again the * signifies cost equals sell price. These extra charges
would lower the overall GPM since we are adding additional cost at
zero profit dollars, which means we are becoming less and less
efficient.
Figure 9 Margin Calculations with DJO and NPT
Category listed on Parameter Sheet
|
Parameter set on Parameter Sheet
|
Cost
|
Sell Price
|
Calculated Gross Profit %
|
Labor Markup %:
|
60%
|
$20.80
|
$33.28
|
37.5%
|
* Non-Productive Time (hours/day):
|
1.00
|
$2.00
|
$2.00
|
0.0%
|
* Direct Job Overhead %
|
15.0%
|
$2.40
|
$2.40
|
0.0%
|
Figure 9 "Margin Calculation with DJO and NPT" can
be
shown as follows:
1. Raw Rate is $16.00 per hour for 1 hour times 1 plus 30% Burden
Rate = $20.80 cost
$20.80 cost times 1 plus 60% markup = $33.28 sell price
2. NPT cost $2.00 per hour for 1 hour with no markup = $2.00
cost
$2.00 cost times 0% markup = $2.00 sell price
3. DJO is $16.00 times 15% DJO markup for 1 hour = $2.40 cost
$2.40 cost times 0% markup = $2.40 sell price
4. The Total Raw Labor Rate is $16.00 per hour
5. The Total Burden Rate is $25.20 per hour ($20.80 raw plus $2.00
NPT plus $2.40)
6. The Total Sell Rate is $37.68 per hour ($33.28 plus $2.00 NPT
plus $2.40 DJO)
Usually not all workers are subject to these added NPT
costs. Therefore, for extremely competitive situations we can remove
the NPT dollar amount for highly efficient technicians from the bid
rate. In fact, we may want to consider plus/minus capabilities to
account for future expected labor cost increases, like upcoming
raises during the project duration.
Figure 10 Labor Cost Summary Sheet
Employee Classification
|
Total labor Hours
|
Base Raw Rate per hour
|
* Non-Productive Charge per hour
|
*Direct Job Overhead Cost (DJO) per hour
|
*Plus Extra Labor Cost per hour
|
Preburden Labor Rate per hour
|
Burdened Labor Rate per hour
|
Albert
|
1.0
|
$16.00
|
$2.00
|
$2.40
|
$(2.00)
|
$18.40
|
$23.20
|
The negative
$(2.00) at the "Plus Extra Labor Cost per
hour" input section should remove the value input by the NPT of $2.00
per hour. For many bids we mark the NPT for 1.00 hour per hour and
decide at the Summary Sheet if we want to include/exclude a NPT
figure for each technician.
Figure 11 Margin Calculations with DJO and NPT minus
Extra Cost
Category listed on Parameter Sheet
|
Parameter set on Parameter Sheet
|
Cost
|
Sell Price
|
Calculated Gross Profit %
|
Labor Markup %:
|
60%
|
$20.80
|
$33.28
|
37.5%
|
* Non-Productive Time (hours/day):
|
1.00
|
$2.00
|
$2.00
|
0.0%
|
* Labor - Extra Cost:
|
($2.00)
|
($2.00)
|
($2.00)
|
0.0%
|
* Direct Job Overhead %:
|
15.0%
|
$2.40
|
$2.40
|
0.0%
|
Example 1 of raw labor rates, NPT, extra cost and
DJO
1
|
Albert ($16.00/hour) will be used for 2 hours
|
2
|
Bryan ($12.00/hour) will be used for 3 hours
|
3
|
Charlie ($7.00/hour) will be used for 1.5 hours
|
4
|
NPT is 1.00 per hour for all technicians
|
5
|
We will negate the NPT charge for Bryan
|
6
|
Charlie will get a raise of $0.25 per hour just after the job
starts
|
Figure 12 Example Burden Calculation with DJO, NPT and
Extra Costs
Employee Classification
|
Total labor Hours
|
Base Raw Rate per hour
|
* Non-Productive Charge per hour
|
*Direct Job Overhead Cost (DJO) per hour
|
*Plus Extra Labor Cost per hour
|
Preburden Labor Rate per hour
|
Burdened Labor Rate per hour
|
Albert
|
2.0
|
$16.00
|
$2.00
|
$2.40
|
|
$20.40
|
$25.20
|
Bryan
|
3.0
|
$12.00
|
$1.50
|
$1.80
|
$(1.50)
|
$13.80
|
$17.40
|
Charlie
|
1.5
|
$7.00
|
$0.88
|
$1.05
|
$0.25
|
$9.18
|
$11.28
|
If Example 1 was only labor (no material or other
costs) the final GPM and averaged sell labor rate would be $27.81 per
hour:
Figure 13 Total Sell and GPM
Category listed on
Parameter Sheet
|
Parameter set on
Parameter Sheet
|
Cost
|
Sell Price
|
Calculated
Gross Profit %
|
Labor Markup %:
|
60%
|
$102.05
|
$163.28
|
37.5%
|
* Non-Productive Time (hours/day):
|
1.00
|
$9.81
|
$9.81
|
0.0%
|
* Labor - Extra Cost:
|
($4.13)
|
($4.13)
|
($4.13)
|
0.0%
|
* Direct Job Overhead %:
|
15.0%
|
$11.78
|
$11.78
|
0.0%
|
Note: * Non-productive Time, *Extra Labor Cost and *DJO have
a zero (0%) GPM Markup
|
$119.51
|
$180.74
|
33.9%
|
Figure 14 Total Labor Rates
Raw Labor Cost/Hr:
|
$12.08
|
Burden Labor Cost/Hr:
|
$18.39
|
Labor Sell per Hour:
|
$27.81
|
Labor Hours:
|
6.5
|
Does not include Sub-Contractor Labor
price |
The Labor Sell rate can easily be used if any add-on
work is applied to this project. Assuming we use Albert, Bryan and
Charlie, a job estimates at 35 labor hours could be quoted at $973.35
(35 x $27.81) with little seat-of-the-pants input. The 33.9% GPM
(gross profit margin) is very healthy for a company financially.
Personal Note: many companies tell me they easily get 35% plus GPM on
all their projects. But after using the BidPro software, find they
are averaging 20% - 30% GPM. Remember, consistency in pricing and
quality of work will take the company along a strong financial
path.
Three additional items can add to the cost of labor: Prevailing
Wage, Premium Wage and payroll taxes (if paid up front). Prevailing
Wage - usually relating to government and school type jobs, dictate
the pay rate for your technician by time-in-grade. There are two
methods to handle these cost items: add a blanket dollar amount to
all technicians (say $2.50 per hour) or calculate each technician (or
groups or areas) at the Prevailing Wage and plug those numbers into
the raw labor rate.
Figure 15 Prevailing Wage add
Prevailing Wage:
|
yes
|
Prevailing Wage (add $ per hour):
|
$2.50
|
If we continue to utilize the Example 1 input, the
Labor Summary would reflect the $2.50 per hour increase for each
technician.
Figure 16 Example Burden Calculations with DJO, NPT, Prevailing Wage
and Extra Costs
Employee Classification
|
Total labor Hours
|
Base Raw Rate per hour
|
* Non-Productive Charge per hour
|
Prevailing Wage per hour
|
*Direct Job Overhead Cost (DJO) per hour
|
*Plus Extra Labor Cost per hour
|
Preburden Labor Rate per hour
|
Burdened Labor Rate per hour
|
Albert
|
2.0
|
$16.00
|
$2.00
|
$2.50
|
$2.40
|
|
$22.90
|
$28.45
|
Bryan
|
3.0
|
$12.00
|
$1.50
|
$2.50
|
$1.80
|
$(1.50)
|
$16.30
|
$20.65
|
Charlie
|
1.5
|
$7.00
|
$0.88
|
$2.50
|
$1.05
|
$0.25
|
$11.68
|
$14.53
|
SUB-TOTALS
|
6.5
|
$78.50
|
$9.81
|
$16.25
|
$11.78
|
$(4.13)
|
$17.26
|
$21.64
|
The associated labor rate would also reflect the added
Prevailing Wage amount:
Figure 17 Total Labor Rates
Raw Labor Cost/Hr:
|
$12.08
|
Burden Labor Cost/Hr:
|
$21.64
|
Labor Sell per Hour:
|
$33.01
|
Labor Hours:
|
6.5
|
The Total Sell and GPM figures:
Figure 18 Total Sell and GPM
Category listed on
Parameter Sheet
|
Parameter set on
Parameter Sheet
|
Cost
|
Sell Price
|
Calculated
Gross Profit %
|
Labor Markup %:
|
60%
|
$102.05
|
$163.28
|
37.5%
|
* Non-Productive Time (hours/day):
|
1.00
|
$9.81
|
$9.81
|
0.0%
|
Prevailing Wage:
|
$2.50
|
$21.13
|
$33.80
|
37.5%
|
* Labor - Extra Cost:
|
($4.13)
|
($4.13)
|
($4.13)
|
0.0%
|
* Direct Job Overhead %:
|
15.0%
|
$11.78
|
$11.78
|
0.0%
|
Note: * Non-productive Time, *Extra Labor Cost and *DJO have
a zero (0%) GPM Markup
|
$140.64
|
$214.54
|
34.4%
|
The added prevailing wage cost has the usual 60% sell
markup. Note the higher GPM of 34.4% (versus 33.9%), which reflects
the profit percent of prevailing wage at 37.5%. The Premium Time
markup (expressed as a percent) can cover holidays, union, emergency
or weekend work. If premium time were chosen, all technician raw
labor rates would have risen 10% (i.e., Albert would add $1.60).
Figure 19 Premium Time
Premium Time:
|
yes
|
Premium Time Differential (per/hour):
|
10%
|
The final labor cost item could be the labor tax (if
applicable in your area). Some companies pay these taxes up front, as
a cost. Some companies always markup all costs. However, for this
example we will calculate tax only on material.
Figure 20 Labor Tax as cost
Location Material Sales Tax %:
|
7.75%
|
Tax on Material (M) or Labor and Mat (LM):
|
M
|
Pay Sales Tax Up front as Cost ?:
|
no
|
Material Sell Prices: The approaches to material sell
prices are threefold:
1. List quantity and material cost along with a standard material
markup
2. List same as Item#1 but make each markup unique.
3. Combine the Item#1 and #2.
Figure 21 Material Markup Percent
This standard
markup will be applicable to all
material entered for your project. If there is a special widget that
your company buys but wants to sell at a higher markup, the "Desired
Markup %" unique section can be utilized. It will negate the standard
markup and use the unique input value.
Figure 22 Material Cost and Sell Prices
Quantity
|
Material Description
|
Unit Cost ($)
|
Parameter Markup %
|
Desired Markup %
|
Unit Sell Price ($)
|
Extended Sell Price ($)
|
Extended Cost ($)
|
12,000
|
CAT5e PVC cable
|
0.06523
|
40%
|
|
0.091322
|
1,095.86
|
782.76
|
1
|
Special widget
|
250.00
|
|
60%
|
400.00
|
400.00
|
250.00
|
75
|
cable hanger group
|
2.71
|
40%
|
|
3.794
|
284.55
|
203.25
|
75
|
ceiling grid wires
|
0.00
|
40%
|
|
0
|
$- 0
|
$- 0
|
75
|
J hooks and wire clip
|
0.00
|
40%
|
|
0
|
$- 0
|
$- 0
|
75
|
wood screw mount
|
0.00
|
40%
|
|
0
|
$- 0
|
$- 0
|
end
|
|
252.77523
|
|
|
403.885322
|
1,780.41
|
1,780.41
|
The list of material items (description, vendor,
supplier, colors and part numbers) can be stored under separate
covers. Simply call up the specified material description/price sheet
and copy to the material sheet. Add quantities and desired markups
for this project and you have a comprehensive material layout. Two
items can add costs to your material sheet:
1. Miscellaneous Material
2. Shipping or Freight Charges
Miscellaneous Material is a percent of the Total Material Cost to
account for cable hangers, cable ties, setup, ceiling tile damage,
oversight, etc. The industry average miscellaneous material cost is
10 percent of the total material cost. Set your specific values.
Figure 23 Miscellaneous Toggle
Misc. Material (% of Material Total):
|
10%
|
Freight percentage is calculated from the Total
Material Cost (with miscellaneous material charges included) to
account for shipping handling, warehousing and pickup. The industry
average freight cost is five percent of the total material cost. Set
your specific values.
Figure 24 Freight Toggle
Freight % (average 5%):
|
5%
|
Since we are using the Example 1 labor hours of 6.5,
the material - labor skew for this example may not be accurate. It
will take about 80 hours to install 12,000 feet of communications
cabling (average run 152 feet), 75 jacks and associated faceplates.
With a CAT5e patch panel the total sell price of this project may be
around $7,000. See http://www.profitdeveloper.com for CablePro
software package.
The cost of our project is $1,578.44, which has accounted for
material, labor and freight charges. The sell price of $2,436.27 will
provide us with $706.06 in profit (tax excluded) or 30.9% GPM.
Figure 25 Margin Calculations for Material, Labor and
Freight
Category listed on Parameter Sheet Parameter
|
set on Parameter Sheet
|
Cost
|
Sell Price
|
Calculated
Gross Profit %
|
Material Markup %:
|
40%
|
$1,236.01
|
$1,780.41
|
30.6%
|
Misc. Material (% of Material Cost):
|
10%
|
$123.60
|
$178.04
|
30.6%
|
Pay Sales Tax Up front as Cost:
|
no
|
|
|
|
Location Material Sales Tax %:
|
7.75%
|
|
$151.78
|
|
Labor Markup %:
|
60%
|
$102.05
|
$163.28
|
37.5%
|
* Non-Productive Time (hours/day):
|
1.00
|
$9.81
|
$9.81
|
0.0%
|
Prevailing Wage:
|
$2.50
|
$21.13
|
$33.80
|
37.5%
|
Premium Time:
|
10%
|
$10.21
|
$16.33
|
37.5%
|
* Labor - Extra Cost:
|
($4.13)
|
($4.13)
|
($4.13)
|
0.0%
|
* Direct Job Overhead %:
|
15.0%
|
$11.78
|
$11.78
|
0.0%
|
Pay Sales Tax Up front as Cost:
|
no
|
|
|
|
Location Labor Sales Tax:
|
no
|
|
|
|
Freight % (average 5%):
|
5%
|
$67.98
|
$95.17
|
28.6%
|
Note: * Non-productive Time, *Extra Labor Cost and *DJO have
a zero (0%) Gross Profit Margin Markup
|
$1,578.44
|
$2,436.27
|
30.9%
|
Is this the end of cost inputs? No. We can still
account for the following direct cost items:
1. Subcontractor material and labor cost
2. License and permit costs
3. Mileage, per diem and parking charges
4. Material cost items at pass-through or no-markup rates
The intent of accounting for all anticipated costs is
to not to get caught with unexpected costs that eat away profits.
Assume we have provided for all cost inputs to this project, but have
learned a competitor may bid this project near $2,100.00. Beside the
obvious impact of losing the bid to a lower bid contractor how does
the $2,100.00 impact our profit margin assuming we try to match that
lower bid?
Figure 26 Sell Price Information
Labor Hours
|
6.5
|
Labor Sell Price/Hour
|
$30.62
|
Enter desired sell price ($),
|
#4 will calculate Gross Profit (%)
|
Material
|
$1,688.13
|
Desired
Sell Price (>$ 0.00):
|
$2,100.00
|
Tax
|
$130.83
|
Program estimates gross profit margin to be:
|
19.8%
|
Labor
|
$199.00
|
Note 1: Backward Accuracy +/- 1%
|
$2,100.00
|
Other
|
$82.04
|
|
|
Subcontractor
|
0
|
Our profit margin would drop to 19.8% with only
$390.74 profit dollars. Obviously this project sell price would
require management override signatures in order to bid the project.
Assume management has insisted the GPM must be 25%, regardless of the
lower bidder, and asks you to sell the customer on the difference.
Utilize the following GPM input portion to attain the desired sell
price.
Figure 27 Sell Price based on GPM
Labor Hours
|
6.5
|
Labor Sell Price/Hour
|
$32.72
|
Enter desired gross profit (%),
|
#3 will calculate Sell Price ($)
|
Material
|
$1,804.21
|
Desired Gross Profit % (1% to 99%)
|
25.0%
|
Tax
|
$139.83
|
Program estimates sell price to be:
|
$2,244.41
|
Labor
|
$212.69
|
Note 1: Backward Accuracy +/- 1%
|
$2,100.00
|
Other
|
$87.68
|
|
|
Subcontractor
|
0
|
Our sell price now will be $2,244.41 with $526.15 in
profit dollars at 25% GPM. This sell amount difference of $144.41
above the lower bidder may provide discussions with your management,
estimators or the customer. Many companies have taken their cost/sell
pricing sheet to their construction loan companies in order to show
planned profits; bankers love profits!
This standardized bidding process is available in a Microsoft
Excel-based software package, BidPro from
http://www.profitdeveloper.com. Any company bidding a variety of
products or services can use BidPro. In addition, BidPro can be used
as an input to TrakPro in order to track
actual-costs-to-contract-costs and provide for financial WIP
information like cash position and over/under billing. The complete
software suite of five packages; BidPro, TrakPro, CablePro,
ConduitPro and AttendancePro are available for sale.
Conclusion
Over the years, many companies have bid cabling projects, by
whatever mechanism, with usually good profit success. The business
climate post-2002 has been somewhat limited for some contractors who
failed to remain competitive in their bids.
Today's communications cabling contractor must:
1. Standardize the bidding process to assure proper cost
pictures
2. Provide fast and accurate cost/sell information
2. Work with suppliers for proper products, pricing and shipping
information
3. Provide technicians with formal training programs by BICSI and
many university/technical schools in order to install all products
with minimal or no problems
Your company will need to quickly and accurately ascertain a
competitor's bidding tier in order to better prepare your winning
proposal. Remember information resource management (IRM) and computer
influenced decision-making are being utilized by your
competitors.
About the Author
Peter Buitenhek has been involved with contracts and estimating
projects for nearly 30 years. In 1996, Peter started developing a
suite of software products to consistently bid and track projects
keeping the PROFIT picture always in sight. This software utilizes
simple parameter and project specific entry forms to allow project
bidding and tracking of any type of product/service combination from
one dollar to $99.9 million.
|